July 3, 2024

Hinkley C's Second Reactor: Faster and Smarter Construction

Hinkley C's Second Reactor: Faster and Smarter Construction

At Hinkley Point C, construction is moving ahead at an unprecedented pace, with the second reactor unit being built 20% to 30% faster than the first. This acceleration is a testament to the construction teams’ ability to learn and adapt, driving efficiency through innovation and experience.

Optimising Reactor Construction

The faster progress on the second reactor unit is largely due to the lessons learned during the construction of the first unit. The teams have refined their processes, adopting new methods and techniques that significantly reduce construction time while maintaining the highest standards of quality and safety.

Key Innovations Driving Efficiency

One of the most impactful changes is the adoption of a new welding method, which is four times faster than the method used on the first reactor. This innovation not only speeds up the construction process but also improves the consistency and quality of the welds, ensuring the long-term reliability of the reactor.

Another major factor contributing to the accelerated pace is the increased use of modularisation. By prefabricating components in controlled factory conditions, more work can be completed off-site, reducing the time needed for on-site assembly. This approach not only speeds up construction but also enhances safety and quality by minimising the complexity of on-site operations.

Key Benefits

  • Increased Speed: Construction of the second reactor unit is progressing 20% to 30% faster, thanks to innovative techniques and improved processes.
  • Improved Efficiency: New welding methods and modularisation reduce on-site time and increase the quality and consistency of the construction work.
  • Future Impacts: The innovations and efficiencies developed at Hinkley Point C are already being incorporated into plans for the construction of future reactors at Sizewell C in Suffolk, ensuring even faster and more efficient builds in the future.

The accelerated progress at Hinkley Point C is setting a new standard for nuclear reactor construction, showcasing how innovation and experience can dramatically improve efficiency. The success of these new methods is not only benefiting the current project but is also informing future nuclear builds, including the upcoming reactors at Sizewell C.

Elevate your bids

We're dedicated on staying ahead with the latest news and market trends, using insights to shape your bidding strategy. Choose us for your next bid, where our comprehensive services include bid strategy, bid management, and design. With a remarkable 96% success rate in 2023, we're here to guide you seamlessly along the path to success.

Our results in 2023

Success in Numbers

96%
Success Rate
90%
Repeat Business
CONTACT US

Get in Touch

Find out how we can remove the burden of writing tender responses.

webid consult office picture